Which Capability Area is recommended for organizations dealing with challenges like missed deadlines due to poor estimates?

Prepare for the Capability Maturity Model Integration (CMMI) Associate Exam with our quiz. Dive into flashcards and multiple-choice questions that include hints and explanations. Ace your exam effortlessly!

The recommended Capability Area for organizations facing challenges such as missed deadlines due to poor estimates is Planning and Managing Work (PMW). This area focuses on defining and managing project plans, schedules, and resources effectively to ensure that work is aligned with organizational goals and deliverables are met on time.

By emphasizing effective planning, PMW helps organizations establish realistic schedules and resource allocations based on accurate estimates. This proactive approach to managing work allows teams to foresee potential issues, adjust plans accordingly, and optimize performance. As a result, organizations can minimize the risks of missed deadlines and improve overall project execution.

In contrast, the other Capability Areas address different aspects of organizational processes. For instance, Decision Analysis and Resolution (DAR) focuses on making informed decisions based on systematic analysis, which can support planning but does not directly address the estimation process itself. Implementation Infrastructure (II) pertains to the technical environment and tools necessary to support project work but does not specifically tackle planning or estimation issues. Process Asset Development (PAD) deals with the creation and management of process assets that can aid in process improvement, yet it does not specifically address the timely execution of work or the accuracy of estimates. Thus, while they play important roles in overall organizational effectiveness, they do not directly target the challenges related